The construction of the station «Olympic Park» has began in the Imereti lowland

Specialists of NPO «Mostovik» are already constructing the pile foundation of the railway station. The «Olympic Park» Station, designed by «Studio 44», will be ready in 2012.

August 25, 2010

Construction of infectious hospital near Dagomys

New infectious hospital is a complex of low buildings on the eastern bank of Dagomys river designed for 300 cots: 150 adults and 150 children.

August 26, 2010

Public Hearings on August 25, 2010

Consideration was given to three issues: the reconstruction project of the coastal embankment, the project of a quarter of residential development on Urozhaynaya street and the expansion project for power substation «Poselkovaya» in Krasnaya Polyana.

August 27, 2010

The construction of foundation slab of the Little Ice Arena is conducted

Construction of the arena has began in June 2010 with the ceremonial laying of a symbolic puck. Project completion is scheduled on Summer of 2012. After the Games, the stadium can be moved to other region.

«the Architecture of Sochi»

Rate this post
Предыдущая статьяНа месте круглых касс рядом с жд вокзалом появится Park Inn City Centre Sochi
Следующая статьяИгорь Ярошевский: начало пути

ОСТАВЬТЕ ОТВЕТ

Получать новые комментарии по электронной почте. Вы можете подписатьсяi без комментирования.